Light-rail construction lags on campus

Light rail construction in the intersection of Oak Street and Washington Avenue was supposed to be completed in November. (Photo by Marisa Wojcik)

January 29, 2012

Complications with construction on the Central Corridor light-rail project have caused contractors to miss major deadlines in the University of Minnesota campus area.

Although the light-rail project is 40 percent complete overall, construction around campus is actually behind, forcing the Metropolitan Council and Ames/McCrossan Joint Venture — the contractor team building the Minneapolis portion of the line — to push some deadlines further into 2012.

One part of the project that missed its deadline is the Oak Street intersection. The initial contract between the Met Council and Ames/McCrossan JV required the entire intersection to be completed by Nov. 30, 2011, according to Sandy Cullen, assistant director of Transportation Systems Design for Parking and Transportation Services at the University.

It included placing tracks along both sides of the intersection and completing final pavement and sidewalk connections.

Currently, only the west half of the Oak Street intersection and track installation is completed. The deadline for the east half of the intersection and track installation has been extended to June 15, Met Council spokeswoman Laura Baenen said.

The opening of Washington Avenue between Walnut and Oak Streets was also behind schedule. Although it’s open now, it did not meet the 150-day completion requirement stipulated in the contract for work in front of businesses, Baenen said.

Work was delayed on the East Bank for a number of reasons, including numerous conflicts moving private utilities out of the work zone, field issues like unknown utilities found under the ground and construction work constraints imposed by the University, Baenen said.

These constraints restricted the hours crews could work during the day and limited the amount of vibrations the construction could produce. The University permitted the crews to work Monday through Friday from 5 a.m. to 2 p.m. and Saturday from 5 a.m. to 1 p.m., Baenen said.

“You’re losing several hours of daylight every single day — almost another full day’s worth of work every single day,” Baenen said.

But Kathleen O’Brien, vice president of University Services, said it would be a “false characterization” to say the University’s restrictions are a reason the project has missed deadlines. She said those constraints were put in place to mitigate effects on neighboring research facilities.

“This agreement was well known before the contractor was doing their schedule,” O’Brien said.

Future projects may also be affected because of the delays in the 2011 season. The contractor team is reviewing construction deadlines for the 2012 season and may make further changes, Cullen said.

The north sidewalk on Washington Avenue between Oak and Church Streets is supposed to be mostly completed by Aug. 15, along with major work on the East Bank between Pleasant and Oak Streets. But based on the delays, it will be difficult to meet those deadlines, Baenen said.

Both sides are meeting to discuss the lessons they have learned over the course of construction thus far.

“We’re working together to ensure that the project gets done on time and in budget and also so the University can continue to conduct its business, teach classes and do research,” O’Brien said.

The St. Paul leg of the project has also experienced numerous delays and compliance complaints, which has frustrated community and city leaders.

The Twin Cities Daily Planet is an edited news source produced by professional journalists working in collaboration with citizen journalists from the local community. We publish original reported news articles, articles republished from media partners, and some content (Free Speech Zone articles, reader-submitted blog entries, comments) that is moderated but not edited. Click here for a complete description of our editorial policies. Support people-powered non-profit journalism! Volunteer, contribute news, or become a member to keep the Daily Planet in orbit.

Comments

Post new comment

The content of this field is kept private and will not be shown publicly.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd> <p> <br> <img> <span> <div>
  • Lines and paragraphs break automatically.
  • You may use [google_ad:ad_slot] to display Google Admanager ads within your content.

More information about formatting options

CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.
Image CAPTCHA
Enter the characters shown in the image.
To prevent automated spam submissions leave this field empty.
workaround

Free Speech Zone

The Free Speech Zone offers a space for contributions from readers, without editing by the TC Daily Planet. This is an open forum for articles that otherwise might not find a place for publication, including news articles, opinion columns, and announcements. The opinions expressed in the Free Speech Zone and Neighborhood Notes, as well as the opinions of bloggers, are their own and not necessarily the opinion of the TC Daily Planet.

Click here to see a display of Twin Cities problem reports, from potholes to neighborhood eyesores. Click here to report a problem. Have you used SeeClickFix? Have you gotten any response from city officials? Let us know - email info@tcdailyplanet.net