Construction of the light rail line 40 percent complete

January 19, 2012

Amid the vast changes and the occasional bout of confusion for University students and faculty, the Central Corridor light-
rail line has begun to take shape.

While adjusting to these changes proved difficult at times, a look down Washington Avenue shows that significant progress has been made during the first full semester of construction.

 According to the Metropolitan Council, the project is now 40 percent complete. A few of the benchmarks met on campus this semester include reconstructing the south side of the Washington Avenue Bridge, installing the first rail on the East Bank and constructing stations on the East Bank in front of Moos Tower and the West Bank between the Cedar and 19th Avenue bridges.

Construction crews will continue to work near campus on the Washington Avenue Bridge and West Bank station throughout the winter. Crews will be back on the East Bank in late March, said Met Council spokeswoman Laura Baenen.

Pedestrians and bikers were forced to adapt to the changes on campus.

University Police Chief Greg Hestness said traffic issues were persistent in the first few months of construction. The intersection of Pleasant Street and Pillsbury Avenue was especially troublesome, Hestness said.

“It took quite a bit of work to get people to obey and wait their turn,” Hestness said. “Basically at that intersection, everything that could hit each other did hit each other.”

But a new traffic light was erected at that intersection over winter break and will hopefully be operational by Tuesday, Hestness said.

During the coming year, students can expect to see even more changes around campus as the heavy construction stage of the project comes to a close.

Crews plan to complete work on the Washington Avenue transit/pedestrian mall by the end of the year, Baenen said. The mall will stretch from Pleasant to Walnut streets and include 20-foot-wide sidewalks on each end of the station and will be closed to general vehicle traffic.

Construction of the East Bank, West Bank and Stadium Village stations, as well as the Washington Avenue Bridge will also be finished by then. In addition, crews will rebuild underground utilities and install rails in other areas near campus.

Although major construction will be substantially finished by the end of the year, the light rail will not be open until 2014.

Following the heavy construction stage, the rail must undergo systems work (like installing overhead wires) and testing.

The Twin Cities Daily Planet is an edited news source produced by professional journalists working in collaboration with citizen journalists from the local community. We publish original reported news articles, articles republished from media partners, and some content (Free Speech Zone articles, reader-submitted blog entries, comments) that is moderated but not edited. Click here for a complete description of our editorial policies. Support people-powered non-profit journalism! Volunteer, contribute news, or become a member to keep the Daily Planet in orbit.

Comments

Post new comment

The content of this field is kept private and will not be shown publicly.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <ul> <ol> <li> <dl> <dt> <dd> <p> <br> <img> <span> <div>
  • Lines and paragraphs break automatically.
  • You may use [google_ad:ad_slot] to display Google Admanager ads within your content.

More information about formatting options

CAPTCHA
This question is for testing whether you are a human visitor and to prevent automated spam submissions.
Image CAPTCHA
Enter the characters shown in the image.
To prevent automated spam submissions leave this field empty.
workaround

Free Speech Zone

The Free Speech Zone offers a space for contributions from readers, without editing by the TC Daily Planet. This is an open forum for articles that otherwise might not find a place for publication, including news articles, opinion columns, and announcements. The opinions expressed in the Free Speech Zone and Neighborhood Notes, as well as the opinions of bloggers, are their own and not necessarily the opinion of the TC Daily Planet.

Click here to see a display of Twin Cities problem reports, from potholes to neighborhood eyesores. Click here to report a problem. Have you used SeeClickFix? Have you gotten any response from city officials? Let us know - email info@tcdailyplanet.net